Question

Which of the following practices ensures that building systems are designed efficiently, installed appropriately and operate as intended?

A. Buildinq retrocommissioning
B. Building commissioning
C. Negative feedback loop
D. Positive feedback loop

Answer

B. Building commissioning

Explanation

Building commissioning is a quality assurance process that begins during the design phase and continues through construction, occupancy, and operation of the building. It ensures that the building’s systems are designed efficiently, installed correctly, and operate as intended.

The commissioning process involves a series of inspections, tests, and adjustments of building systems, followed by a review of the system design and operation with the building’s operations team.

Building commissioning is a process that verifies all building systems are designed, installed, tested, operated, and maintained according to the owner’s project requirements and design intent. The goal of commissioning is to ensure building systems perform efficiently and as intended.

The key aspects of building commissioning include:

  1. Verifying systems are designed to meet the owner’s project requirements and sustainability goals
  2. Ensuring systems are installed and calibrated correctly per the design documents
  3. Testing systems to validate proper and efficient operation and performance
  4. Providing documentation, training, and a commissioning report to the building owner
  5. Performing periodic commissioning to maintain optimal building performance over time

Commissioning applies to HVAC, lighting, hot water, renewable energy, and other systems. It’s an important quality assurance process for achieving high-performance green buildings.

The other options are incorrect:
A. Retrocommissioning applies to existing buildings to improve performance, not the design/construction phase
C/D. Feedback loops are not directly related to building commissioning as a specific sustainability best practice.

In summary, building commissioning (B) is the key process that ensures building systems are designed efficiently, installed appropriately, and operate as intended from the initial design through the life of the building. It’s an important concept to understand for the LEED Green Associate Exam.