USGBC LEED Green Associate: Correct Order for LEED Certification Process Steps

Discover the correct order of steps in the LEED certification process. Our LEED Green Associate expert provides a clear, detailed explanation to help you succeed.

Table of Contents

Question

LEED certification steps generally proceed in which of the following order?

A. Project Registration, Application Preparation, Submission, Application Review, Certification
B. Application Preparation, Application Review, Project Registration, Submission, Certification
C. Select LEED rating system, Submission, Application Review, Project Registration, Certification
D. Application Preparation, Project Registration, Application Review, Submission, Certification

Answer

The correct order of steps in the LEED certification process is:

A. Project Registration, Application Preparation, Submission, Application Review, Certification

Explanation

This is the correct order of the LEED certification process for most projects. The first step is to register the project on LEED Online and pay the registration fee. The second step is to prepare the application by collecting and uploading the required information and documents according to the chosen rating system and credits.

The third step is to submit the application and pay the certification fee. The fourth step is to undergo the application review by a LEED accredited third party, which may request clarifications or corrections. The final step is to receive the certification decision and the LEED plaque and certificate.

Life-cycle cost analysts of a new construction includes consideration of cost of purchasing window glazing cost of adding accessible parking cost of challenging a real estate tax assessment cost of subsidizing the use of public transportation Life-cycle cost analysis (LCCA) is a method for assessing the total cost of owning a facility or running a project.

It considers all the costs associated with obtaining, owning, and disposing of an investment. The cost of purchasing window glazing is one of the initial costs that affects the energy performance and thermal comfort of a building. Therefore, it is included in the LCCA of a new construction.

The LEED certification process begins with registering the project with GBCI (Green Business Certification Inc.). This involves providing basic information about the project and paying a registration fee.

Next, the project team prepares the LEED certification application. This involves gathering detailed documentation demonstrating how the project meets the requirements of the selected LEED rating system. Common documents include site plans, energy models, water usage calculations, and material specifications.

Once the application is complete, it is submitted to GBCI for review. The GBCI review team carefully evaluates the application to verify that the project meets all prerequisites and enough credits to achieve the targeted level of LEED certification.

After the review, GBCI provides a preliminary ruling indicating which prerequisites and credits have been achieved. The project team has an opportunity to respond to any issues or provide additional documentation.

Finally, once all prerequisites and targeted credits are verified, GBCI issues the official LEED certification at the appropriate level (Certified, Silver, Gold, or Platinum) based on the number of points achieved. The project is then added to the public LEED project directory.

So in summary, the key steps are registering the project, preparing the application with required documentation, submitting it for review, going through the review process, and receiving the final certification – always in that order. Understanding this process is critical for successfully navigating LEED certification.